Our Completed Projects
ANCC-601
Fabrication,
Painting & Erection of 300 ton steel structure @
Joi’amah Gas Plant
Client: Faisal M. Qahtani Sons
Co.
Duration: 10 Months (Feb to Dec
05)
ANCC-602
Welding
of 20” Dia Crude Pipeline (20 km)@ Haradh - Under Saudi Aramco.
Client:
Faisal M. Qahtani Sons Co.
Duration:
15 months (Jul 05 to Oct 06)

ANCC-603
Piping
installation
@
Qassim
Cement
Plant
Client: Amen Engg. Intn’l
Duration: 10 months (Jun 05 ~Mar 06)
ANCC-604
Fabrication,
Painting & Erection of 1,450 ton structure, 50,000 dia-inch
piping & 150 ton cable trays @ Sulfur Factory Dammam-ii
Client: Sulfur
Factory Dammam-II
Duration: 12 months
(Jan to Dec 06)
ANCC-605
Fabrication
of 110,000 dia-inch cs / ss piping @ Tasnee Ethylene
Project Jubail
Client: Contracting &
Trading Co. CAT /Samsung Engg. Saudi Arabia
Duration: 08
months (Jun 06 to Mar 07)

ANCC-606
Fabrication
of Aprox. 800 ton structure @ Fabrication Yard Jubail
Client: Saudi Pan Gulf Co. / Saudi Aramco
Duration: 09 months (Jan to Sep 07)

ANCC-607
Fabrication
of Aprox. 85,000 inch-dia of piping & 28,000 inch-dia site
installation @ Al-waha / Sahara Project- Jubail
Client: Olayan Descon Industrial Co. Jubail- Saudi Arabia
Duration: 12 months(Sep 07 to Aug 08)

ANCC-608
Sand
Blasting & Painting of pipes & pipe spools/ supports (Aprox.
55,000 sq.m) @ Al-waha / Sahara Project- Jubail
Client: Olayan Descon Industrial Co.
Jubail- Saudi Arabia
Duration:
12 months (Jul 07 to Jun 08)

ANCC-609
Fabirication
& installation of Fire Water Sprinkler system(Approx. 8km
piping @ Al-Waha / Sahara Project Jubail)
Client: Olyan Descon Industrial
CO. Jubail -SuadiArab
Duration: 8
months (Jul 08 to Feb 09)

ANCC-610
Civil structure/ block work/ finishing work for nesma workers camp
al-jubail (5,200 sq.meter covered area
Client: Rakan Trading & Contracting Co.
Al-Khobar, Saudi Arabia
Duration: 10 months (June 09 to April 10)
ANCC-611
Fabrication & Welding of APROX. 520 Tons of Steel Structure/Handrails/Ladders & Painting of 750 Tons of Fence at AL-Nemshan Fab. Yard Jubail
Client: Saudi Pan Gulf
Jubail, Saudi Arabia
Duration: 12 months (Jul 09 to Jul 10)
ANCC-612
Blasting &
Painting of PPROX. 30,000 Sq. Mtr. of Steel Structure, Tanks, Handrails, Ladders & Pipes @ MA'ADEN Magnasite Project Al-Madina
Client: Olayan Descon Industrial Co.
Jubail, Saudi Arabia
Duration: 10 months
(Dec 09 to Sep 10)
ANCC-613
Sand Blasting, Painitng, Fabrication and Installation of Fabrication/Storage Hangers APPROX. 950 Sq. Mtr. Structure @ Nemshan Fab. Yard Jubail.
Jubail, Saudi Arabia
Duration: 04 months
(Jun 10to Dec 10)
ANCC-614
150,000 M3 Sand Filling & 50,000 M2 Marl Capping With 20cm Thickness @ ODICO Yard Abu Hadriya.
Client: Olayan Descon Industrial Co.
Jubail, Saudi Arabia
Duration: 02 months
(Oct 10to Nov 10)